Starting a grade business

$
0
0
To start I essentially know nothing about sub grade or final. So obviously I've decided to start a grade company. I have two pieces of equipment, a 740 Volvo grader, and a 272 ssl. I am looking to purchase laser grading equipment for both pieces.

I won't talk actuall dollars as pricing varies by location, but I have narrowed it down to 1000 sq feet per hour for the ssl, and 2000 sqft(?) for the grader.

My questions are does that time include compaction? Should my price include the use of a roller an a labourer? Are companies looking for strictly grading services while providing the material and compaction themselves?

From what I've read the process is 1) remove the top soil 2) bring in suitable fill 3) compact and level fill 4) add a compactedand levelled (+\- 2") layer of gravel for drainage 5) spread and level final grade material

Does all this sound right? Is there anything missing? Am I off on my time estimates?